The Village’s paving contractor is scheduled to perform the following roadway work next week. Please note that all work is weather dependent and may be rescheduled in the event of heavy rain.

Monday, June 22

  • Milling: Harrington Street, Wurts Avenue, North Front Street

Tuesday, June 23

  • Church Street: Milling, full-depth pavement removal on the west side, and subbase installation

Wednesday, June 24

  • Church Street: Fine grading of the subbase and installation of binder asphalt

Thursday, June 25

  • Church Street and North Front Street: Installation of top course asphalt

Friday, June 26

  • Wurts Avenue and Harrington Street: Installation of top course asphalt

Please expect temporary traffic delays and parking restrictions in work areas. Thank you for your patience as these improvements are completed.