The Village of New Paltz would like to alert residents to upcoming milling and paving work on North Chestnut Street and the Main Street intersection.
- Tuesday, 5/12: Milling on North Chestnut from Sunset Ridge Road moving south with single-lane traffic control.
- Wednesday, 5/13: Milling at the Main Street intersection with North & South Chestnut. Detour plan in effect.
- Thursday, 5/14: Paving at the Main Street intersection with the same detour plan in effect.
- Friday, 5/15: Paving on North Chestnut from Stewart’s Gas Station to Sunset Ridge Road with single-lane traffic control.
Please expect delays, follow posted signage, and use caution in work zones.
See attached map/detour plan for traffic routing information.
Notice: Milling & Paving Schedule: North Chestnut St. & Main St. Intersection