As part of the continued water main replacement and repair project, the following road work is scheduled:

North Chestnut Street
October 13–17, 2025

  • Crews will be installing full-depth blacktop in trench areas to prepare for final paving.
  • No road closures
  • No water shut-offs

Traffic control will be in place

South Chestnut Street
October 15–17, 2025

  • Milling and paving will be performed.
  • North end of South Chestnut will be closed with a detour in place
  • Traffic control on the remaining open section
  • No water shut-offs

Please drive with caution and follow posted signs. Thank you for your cooperation.

Notice: Upcoming Road Work for Water Main Replacement and Repair