As part of the continued water main replacement and repair project, the following road work is scheduled:
North Chestnut Street
October 13–17, 2025
- Crews will be installing full-depth blacktop in trench areas to prepare for final paving.
- No road closures
- No water shut-offs
Traffic control will be in place
South Chestnut Street
October 15–17, 2025
- Milling and paving will be performed.
- North end of South Chestnut will be closed with a detour in place
- Traffic control on the remaining open section
- No water shut-offs
Please drive with caution and follow posted signs. Thank you for your cooperation.
Notice: Upcoming Road Work for Water Main Replacement and Repair